Solution
Understanding the set :-
- There are 4 employees - Abani, Bahni, Danni and Tinni supervised by Dhoni
- They did 5 projects in 2020
also, For each of these projects , the starting day was at the beginning of a month and the concluding day was the end of a month.
- The graph shows the percentage of assigned work completed by the employee
- total project-month (in 2020) = sum of the number of months (s)he worked across the five project
- annual completion index = weighted average of the completion percentage (weights being the corresponding number of months (s)he worked in these projects.)
- total employee-month = sum of the number of months four employees worked in this project
- completion index = weighted average of the completion percentage assigned for the employees who worked in this project, with the weights being the corresponding number of months they worked in this project.
This is a Gantt Chart.
A Gantt Chart is a project management tool used to illustrate a project schedule over time.
It shows:
a) Tasks/Projects on the vertical axis (e.g., Project 1 to Project 5).
b) Timeline on the horizontal axis (e.g., Jan 1 – Jan 1 next year).
c)Bars representing the duration and progress of each task.
d)Colors and percentages indicate completion levels or progress status.
This is a data interpretation set,
In this kind of set, after understanding the graph/ chart properly , you will solve it according to the question's demand.
The total project month is the number of months Abani, Bahni, Danni, and Tinni individually worked for all the projects combined :
Abani - 2+2+5 = 9 months
Bahni - 2+4+3 = 9 months
Danni - 3+3+2+1 = 9 months
Tinni - 2+2+3+2 = 9 months.
The total employee month for all the five projects is the sum of the total employee-month is the sum of the number of months four employees worked in this project.
Project -1 = 2+2+2 = 6 months
Project -2 = 3+2 = 5 months
Project - 3 = 2+4+3 = 9 months.
Project - 4 = 5+2+3 = 10 months.
Project - 5 = 3+1+2 = 6 months.
Therefore, only 1 is correct.