When they work alone, needs more time to finish a job than does. They two finish the job in days in the following manner: works alone till half the job is done, then and work together for four days, and finally works alone to complete the remaining of the job. In how many days can alone finish the entire job?
When they work alone, needs more time to finish a job than does. They two finish the job in days in the following manner: works alone till half the job is done, then and work together for four days, and finally works alone to complete the remaining of the job. In how many days can alone finish the entire job?
Solution
Let's break down what happens in this 13-day work sequence:
A works alone until half the job is done
A and B work together for 4 days
B works alone to complete the remaining 5% of the job
We need to find how long B takes to finish the entire job alone.
Let's say A can finish the entire job alone in a days.
Since B needs 25% more time than A:
B's time = A's time + 25% of A's time
B's time = a + 0.25a = 1.25a = days
Work Rates (portion of job completed per day):
A's rate = jobs per day
B's rate = jobs per day
Here's the key insight: What portion of the job do A and B complete together?
A completes: 50% of the job alone
B completes: 5% of the job alone
A and B together complete: 100% - 50% - 5% = 45% of the job
So A and B working together for 4 days complete of the job.
When A and B work together for 4 days:
Combined work rate × Time = Work completed
Let's simplify the left side:
So our equation becomes:
Cross-multiplying:
A takes 16 days to complete the job alone.
B takes days to complete the job alone.
B alone can finish the entire job in 20 days.
In work and time problems, always identify what portion of work each person/combination completes. This helps you set up the correct equations without getting confused by the different working arrangements.