Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days working 5 hours per day to complete the same task. They decide to work together to complete this task. Seema agrees to work for double the number of hours per day as Renu, while Renu agrees to work for double the number of days as Seema. If Renu works 2 hours per day, then the number of days Seema will work, is
Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days working 5 hours per day to complete the same task. They decide to work together to complete this task. Seema agrees to work for double the number of hours per day as Renu, while Renu agrees to work for double the number of days as Seema. If Renu works 2 hours per day, then the number of days Seema will work, is
Entered answer:
Solution
- Renu can complete the work in 15 days working 4 hours/day
- Seema can complete the work in 8 days working 5 hours/day
| Attribute | Renu | Seema |
|---|---|---|
| Days to Complete | 15 | 8 |
| Hours per Day | 4 | 5 |
| Total Hours | 60 | 40 |
To work with whole numbers, we assume total work = LCM(60, 40) = 120 units
| Attribute | Renu | Seema |
|---|---|---|
| Days to Complete | 15 | 8 |
| Hours per Day | 4 | 5 |
| Total Hours | 60 | 40 |
| Total Work | 120 | 120 |
Rate = Total Work ÷ Total Hours
| Attribute | Renu | Seema |
|---|---|---|
| Days to Complete | 15 | 8 |
| Hours per Day | 4 | 5 |
| Total Hours | 60 | 40 |
| Rate (units/hour) | 120 ÷ 60 = 2 | 120 ÷ 40 = 3 |
| Total Work | 120 | 120 |
New working conditions from the problem:
- Renu works 2 hours per day
- Seema works double the hours of Renu → 2 × 2 = 4 hours per day
- Renu works double the days of Seema
| Attribute | Renu | Seema |
|---|---|---|
| Rate (units/hour) | 2 | 3 |
| New Hours per Day | 2 | 4 |
| Daily Work Output | 2 × 2 = 4 | 3 × 4 = 12 |
| Days Working | 2x | x |
We have to find working days of Seema, hence we have to find
| Attribute | Renu | Seema |
|---|---|---|
| Rate (units/hour) | 2 | 3 |
| New Hours per Day | 2 | 4 |
| Daily Work Output | 4 | 12 |
| Days Working | 2x | x |
| Total Work Done | 4 × 2x = 8x | 12 × x = 12x |
Since together they complete the entire work:
Renu's work + Seema's work = Total work
From the table:
Solving:
Answer: Seema will work for 6 days