Skip to main contentSkip to solution

Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days working 5 hours per day to complete the same task. They decide to work together to complete this task. Seema agrees to work for double the number of hours per day as Renu, while Renu agrees to work for double the number of days as Seema. If Renu works 2 hours per day, then the number of days Seema will work, is

Entered answer:

Solution

✅ Correct Answer: 6
  • Renu can complete the work in 15 days working 4 hours/day
  • Seema can complete the work in 8 days working 5 hours/day
AttributeRenuSeema
Days to Complete158
Hours per Day45
Total Hours6040

To work with whole numbers, we assume total work = LCM(60, 40) = 120 units

AttributeRenuSeema
Days to Complete158
Hours per Day45
Total Hours6040
Total Work120120

Rate = Total Work ÷ Total Hours

AttributeRenuSeema
Days to Complete158
Hours per Day45
Total Hours6040
Rate (units/hour)120 ÷ 60 = 2120 ÷ 40 = 3
Total Work120120

New working conditions from the problem:

  • Renu works 2 hours per day
  • Seema works double the hours of Renu → 2 × 2 = 4 hours per day
  • Renu works double the days of Seema
AttributeRenuSeema
Rate (units/hour)23
New Hours per Day24
Daily Work Output2 × 2 = 43 × 4 = 12
Days Working2xx

We have to find working days of Seema, hence we have to find xx

AttributeRenuSeema
Rate (units/hour)23
New Hours per Day24
Daily Work Output412
Days Working2xx
Total Work Done4 × 2x = 8x12 × x = 12x

Since together they complete the entire work:

Renu's work + Seema's work = Total work

From the table:

8x+12x=1208x + 12x = 120

Solving:

20x=12020x = 120

x=120÷20x = 120 ÷ 20

x=6x = 6


Answer: Seema will work for 6 days

Keyboard Shortcuts

  • Left arrow: Previous question
  • Right arrow: Next question
  • S key: Jump to solution
  • Q key: Jump to question